![logo](https://isconsultores.com.uy/web/wp-content/uploads/2019/02/is_consultores_logo-2.png)
CLIENT | MINISTRY OF INTERIOR |
PROJECT | LP 4-2022 - Sanitation and internal sewage system of Penitentiary Center N°22, Department of Rocha. |
DATE | 2022-2023 |
TYPE OF CONTRACT | Executive Project and Construction |
DESCRIPTION | Sanitation network and effluent treatment system; extension of the hydraulic firefighting system; new water supply network, supply and installation of elevated tanks for storage of 40,000 liters of water. |
WORK VOLUME | |
Earthmoving | 7200m3 |
Waterproofing | 2.620m2 - HDPE geomembrane |
Sewer system | 400ml - PVC pipe |
Water supply / fire network | 1160 ml - HDPE electrowelded pipe |
Reinforced Concrete | 70m3 |